TPB-H recommended parameter settings cover for borewell low and full switching points.

Recommended TPB-H Settings: Borewell Tank Switching Points and Run/Rest

Mohit Vekaria
TPB-H recommended parameter settings cover for borewell low and full switching points.

TPB-H recommended parameter settings are a commissioning record for your exact three-phase dol pump starter. Document the tank sensor’s low and full responses, then record the approved run/rest intervals and motor protection settings. Have the installer confirm normal three-phase operation before enabling automatic starts.

TPB-H recommended parameter settings checklist for installation and commissioned defaults.
Record installation settings separately from the values already commissioned.

What belongs on the first-installation checklist?

A borewell installation may start a fill after water is drawn from the receiving tank. To verify the low and full points, record the real water levels and display responses under the installed sensor arrangement rather than relying on an old drawing alone.

Write the panel model and variant as they appear on the label. Add the controller revision and the motor’s rated current and voltage from the nameplate or pump paperwork. The model tells you which functions the panel offers. The actual motor, supply, water source and operating mode determine the settings that belong in the record. Use the revision-matched instructions for the menu labels and save procedure. VUKAR product manuals and parameter reference

Setting What it does What to record
OL / OLT Overload current threshold and delay before an overload trip. Approved amps (A) and seconds (s).
DR / DRT Low-current threshold for dry-run detection and its own trip delay. Approved amps and seconds.
HIU / LOU High and low supply-voltage limits. Both limits in volts (V).
Three-phase supply The installer confirms phase conditions and normal motor operation before automatic starts. Commissioned phase check and any observed indication.
Tank inputs and mode The commissioned level-control arrangement makes a fill request and ends it at the full point. Actual low and full response, installed sensor layout, and selected mode.
RUN / RST Run and rest lengths for the commissioned repeating cycle. Both durations in minutes and the exact labels shown.

Read current limits and delays as pairs

OL and DR are current limits. OLT and DRT are delays. With overload protection, the controller looks for current above the approved overload limit for the associated time. With dry-run protection, it looks for current below its approved threshold for the corresponding time. A short change in the current reading and a continuing condition tell the controller different things. Record the limit and delay together so the next installer can see both parts of the decision.

TPB-H recommended parameter settings showing overload and dry-run current limits with their delays.
Use amps for OL and DR and seconds for OLT and DRT.

Keep the two voltage limits in the same record, with HIU for the upper limit and LOU for the lower limit. A voltage shown on the front display is the reading at that moment. Write a measured reading and a saved limit in different fields. If a protection trip repeats, note the displayed indication and the conditions around the stop so an installer can investigate the motor, supply or water source.

Have a qualified installer choose protection values using the actual motor and supply. Values from a different pump or controller revision can mislead even when the model name looks familiar. Ask the installer to record who approved the final limits and the date they were set. For wiring and work inside the enclosure, use a licensed electrical contractor and have the supply isolated and verified dead. Central Electricity Authority safety regulations

VUKAR TPB-H three-phase starter panel

VUKAR product

TPB-H Three-Phase Starter Panel

For compatible pump installations. See the product gallery and model features for borewell low and full switching points.

View TPB-H

Borewell low and full switching points

TPB-H includes a built-in MCB as well as automatic water-level control. Note the visible breaker state and any fault display separately from the tank switching result. Record the run/rest timing in the mode the installer actually tested.

For the tank control test, the installer observes the actual water levels with the installed level-sensing arrangement in service. Record when the system recognizes a low demand and what happens at the full point. Keep the tank, sensor layout and selected mode on the same line. If the source cannot supply the pump during the test, record that condition before interpreting what happened on the receiving side.

Record RUN and RST using the exact labels shown on your installed controller. In a commissioned repeating cycle, record both run and rest in minutes. Observe a complete run, the normal stop, the rest period and the next permitted start. Use the pump maker’s operating limits and the installer’s observations of water delivery when choosing the cycle. If another mode uses a time differently, record that mode separately.

Before enabling automatic starting, have the installer confirm the supply phases and normal motor operation using the matching equipment instructions. Write the observed phase indication next to the current operating mode. If the phase or voltage indication changes, record the event time and call the installer. Keep the enclosure closed while observing the display.

TPB-H recommended parameter settings test checkpoints for borewell low and full switching points.
The tank switch points, normal cycle and protection indications each need their own entry.

Keep the other applicable values as commissioned

Keep the documented defaults for the exact controller revision or the values the installer already commissioned. If TRQ appears on your panel, leave its starting torque time at that approved value. Keep current-sensor selection, marked CTS where applicable, and current or voltage calibration as commissioned. Those values belong with the installed hardware and measurements. Have the installer review changes using the matching instructions.

The approved restart settings may include a fault delay, memory after an outage or lockout behavior. Ask the installer to write down which options apply and what can happen after a supply interruption or fault. Keep the recorded mode and labels with the values so they still make sense at the next service visit.

Write down what happened during the watched run

If the pump stops while the tank is still low, write the displayed tank state, elapsed run and protection indication. A record of the event is more useful than changing a timer to get another run.

TPB-H recommended parameter settings handover record with model, saved values and watched test.
Keep this information with the pump and panel paperwork.

Keep three things together for handover. First, identify the panel variant, revision, motor and water source. Second, copy the saved settings and units, including the mode that was tested. Third, write when the test started and stopped, what the display showed and any unexpected event. Date the record and add the installer’s name. This gives you a baseline if a motor, sensor or water source changes later.

If the values already in the panel and the settings on an old service sheet differ, keep both records until the installer has identified the current approved set. A note such as “read from panel” or “approved after test” tells you which numbers were observed and which ones were accepted for the installation. Leave a missing unit or value blank until it can be confirmed.

When reporting a problem, send the panel model and revision, motor rating, current mode, display code and the time of the event. Include the saved timer or protection setting that relates to the event and note any recent change in the installation. VUKAR technical support

Review the record again after the pump has worked under its usual conditions. Note any difference between the first test and later operation, including a change in flow, demand or the supply. Keep that observation as a separate dated entry. If an installer changes a setting, keep the reason for the change and the result of the next supervised run with the new record.

Use the TPB-H installation and setup guide for the panel-specific setup sequence and the VUKAR guide to pump timer types for how the different timing modes behave. At the end of the visit, keep the approved settings sheet where the next owner or technician can find it.