For the DM-SP-CCCT-96 recommended parameter settings, on the DM-SP-CCCT-96, confirm single-phase motor protection first, set the actual clock and active days, then choose the clock event and cyclic durations required by the selected mode.
Start with the installed unit
Write down the model and revision from the unit label, the motor nameplate, the type of starter and the normal operating mode. Keep those details together. Two devices with similar front panels can have different menu options. The correct model guide and the current installation record are the references for any actual setting.
Use the product page to identify available functions and the installed revision’s guide for units, menu names and how the selected mode operates.
If the pump, sensor or operating mode changes, keep the previous record. Mark the date of the change and have the installer observe the revised sequence before relying on automatic operation.

Match the meter to the starter circuit
The digital meter belongs to a motor-control arrangement. Have the installer confirm the compatible starter or contactor, the sensing arrangement and the actual device revision. An electrician should document where the meter’s output command goes, and how the installation confirms that the motor received power. Keep the meter’s displayed reading together with the electrician’s observations.
The motor’s rating is only one part of the decision. The installer also needs the supply arrangement, the nameplate current and the operating conditions of the pump. Have them document which readings are normal when water is flowing steadily. If the meter shows a value that differs from its earlier baseline, record the conditions and leave the calibration decision to the installer.
Set the clock before using a schedule
A clock event uses a time of day, such as 06:00. RUN and RST are elapsed durations, such as 10 minutes. Read the displayed time, weekday and enabled days together. A saved event can show the correct time yet remain inactive because the wrong day or mode is selected. Begin with one event the operator can safely observe.
Watch the opening and closing of the first window and record the actual behavior. If a pump is already running near closing time, use the installed revision’s instructions to determine how that mode handles the boundary. Write down whether it stopped, completed the current run or waited for a later permission. Test the specific sequence before adding overlapping events or leaving it unattended.
Choose RUN and RST from the water supply
RUN is the elapsed pump-on time. RST is the planned pause between cyclic runs in the selected mode. Choose RUN based on how long the source can deliver a steady flow, the space available where the water goes, and the motor maker’s permitted operating conditions. For RST, consider how long the source needs to recover and any minimum time between starts for the motor.
To estimate starts per hour during an uninterrupted cycle, add RUN and RST in minutes and divide 60 by the total. For example, 10 minutes on and 20 minutes off gives about two planned starts per hour. These are example values. Include any separate starts from other controls, power recovery or fault recovery when the installer reviews the motor’s actual start frequency.
What to observe on this model
On this single-phase meter, verify normal motor readings before the first clock event. If an event is due but the motor stays off, record three observations. Note what the display says, whether the starter visibly responds and whether water arrives. Verify one clock boundary and one RUN/RST transition separately before using an automatic schedule.
Use one entry for the clock or day and another for elapsed minutes. Record the selected window, any timer pause and the motor response separately. A later start is easier to explain when the log shows which of those conditions changed first.

Use the motor and supply limits
Have the electrician match the motor’s nameplate and the controller’s sensing arrangement before setting overload, dry-run or voltage protection. A setting copied from a different pump can be unsuitable even when the pumps have the same horsepower. Ask the electrician to record the approved values, their units and which manual or measurement they used. Keep the previous approved values in the record if a setting needs to be changed.
Observe normal operation from a dry and safe place with the enclosure closed. Changes to wiring, live measurements, current sensing, protection and automatic restart belong with the installer. If a fault reappears, record the indication and stop using automatic operation until the cause has been assessed. Use the product instructions and the applicable electrical safety rules for installation and service.
Follow the command to the pump
A controller can show a request while the motor is still off. A starter switches motor power when the control circuit permits it. Observe the display, the starter’s visible response and water delivery as separate facts. These observations give the electrician a place to start without asking you to open the enclosure or touch conductors.
If the display shows that the pump should be running but there is no water, write down whether you could see or hear the motor run from a safe location. If the motor runs but delivery is absent or weak, record how long it ran and when the flow changed. Keep the display photo and the times together so the installer can compare them with the actual settings.
Record what happens after an interruption
An automatic restart can have several conditions. If power returns, a permitted start may depend on the mode, restart settings and normal protection conditions. Some configurations also retain earlier timing information. Use the revision guide and ask the installer to explain the behavior for the mode you actually use. Keep the area around the pump and moving parts clear during supervised testing.
If the pump was waiting before an interruption, write down the time of the interruption, the display after power returned and the actual next start if it occurred. Ask the installer to record how a normal cyclic rest differs from a fault recovery wait. Leave restart settings at the approved values until the behavior is understood and tested.
What to record
| Water and source | Actual tank level or water delivery, and when it changed. |
|---|---|
| Controller | Active mode, saved value or visible indication and its unit. |
| Starter and motor | Actual start and stop, and first permitted restart where applicable. |
Make a two-line event record. In the first line write the expected result and the setting that should produce it. In the second line write the actual time, visible indication and observed water delivery. If an observation is missing, leave that field blank and tell the installer.

Change one condition between watched tests
Begin a test with the mode and relevant settings written down. Change one approved timing or operating condition at a time with the installer. Then observe the pump from the start permission through the actual stop. If two settings change together, a normal or unexpected result is harder to explain later.
Use one record for the expected result and one for what really happened. For a clock event include the active day and time. For a level event include the physical water level and display. For a cyclic stop include actual elapsed minutes. When an event repeats, compare those records before requesting another setting change.
Prepare the installation for a watched test
Choose a time when the source has water, the receiving point has room for delivery and the operator can observe from a safe place. Agree with the installer on what counts as a successful start and stop. Use the normal operating controls. Have the installer handle any changes to the electrical circuit or protection settings.
Tell everyone working near the pump when an automatic start could occur. Keep the enclosure closed while observing the display. If the observed behavior differs from the manual or the approved record, stop the test in the normal safe way and write down what happened before any values are changed.
Keep a record another operator can use
Write the model and revision, the motor details, the saved mode and the approved values at the top of the record. Under that, note actual start and stop times, any physical tank level or source condition, the display at the time and the result of the test. If the installed setup uses automatic restart, include the first permitted restart and what triggered it.