BOM-H recommended parameter settings cover for timed stop and motor protection.

Recommended BOM-H Settings: Protection Limits and Timed Stop

Mohit Vekaria
BOM-H recommended parameter settings cover for timed stop and motor protection.

BOM-H recommended parameter settings are a commissioning record for your exact single-phase borewell pump starter. Record the overload and dry-run limits with their delays, the high and low voltage limits, and the saved RUN duration. Use the timed-stop mode documented for your panel revision and watch the first run from start to stop.

BOM-H recommended parameter settings checklist for installation and commissioned defaults.
Record installation settings separately from the values already commissioned.

What belongs on the first-installation checklist?

A borewell fills an overhead tank when someone starts the pump. The amount of free space can change between fills. Record the starting tank level with the stop time so a later service visit can tell whether the pump stopped on time or the tank simply started with more water in it.

Write the panel model and variant as they appear on the label. Add the controller revision and the motor’s rated current and voltage from the nameplate or pump paperwork. The model tells you which functions the panel offers. The actual motor, supply, water source and operating mode determine the settings that belong in the record. Use the revision-matched instructions for the menu labels and save procedure. VUKAR product manuals and parameter reference

Setting What it does What to record
OL / OLT Overload current threshold and delay before an overload trip. Approved amps (A) and seconds (s).
DR / DRT Low-current threshold for dry-run detection and its own trip delay. Approved amps and seconds.
HIU / LOU High and low supply-voltage limits. Both limits in volts (V).
RUN Elapsed run duration in the applicable auto-off mode. Saved minutes (min), start time and observed stop.

Read current limits and delays as pairs

OL and DR are current limits. OLT and DRT are delays. With overload protection, the controller looks for current above the approved overload limit for the associated time. With dry-run protection, it looks for current below its approved threshold for the corresponding time. A short change in the current reading and a continuing condition tell the controller different things. Record the limit and delay together so the next installer can see both parts of the decision.

BOM-H recommended parameter settings showing overload and dry-run current limits with their delays.
Use amps for OL and DR and seconds for OLT and DRT.

Keep the two voltage limits in the same record, with HIU for the upper limit and LOU for the lower limit. A voltage shown on the front display is the reading at that moment. Write a measured reading and a saved limit in different fields. If a protection trip repeats, note the displayed indication and the conditions around the stop so an installer can investigate the motor, supply or water source.

Have a qualified installer choose protection values using the actual motor and supply. Values from a different pump or controller revision can mislead even when the model name looks familiar. Ask the installer to record who approved the final limits and the date they were set. For wiring and work inside the enclosure, use a licensed electrical contractor and have the supply isolated and verified dead. Central Electricity Authority safety regulations

VUKAR BOM-H single-phase borewell starter panel

VUKAR product

BOM-H Single-Phase Starter Panel

For compatible borewell pumps. See the product gallery and model features for timed stop and motor protection.

View BOM-H

Timed stop and motor protection

BOM-H has a built-in miniature circuit breaker, or MCB. Keep its identification separate from the electronic overload and dry-run settings. At handover, ask the installer to point out the normal stop control and identify the protection device without opening the panel.

Set the RUN duration for a watched timed-stop test in the mode approved for the installed revision. Start with water available and enough receiving space. Read the saved value back in minutes before the run. Record the time the motor actually starts and the time it stops. If it runs beyond the planned stop, use the normal stop control from a dry, safe location and have the installer review the selected mode and saved duration.

BOM-H recommended parameter settings test checkpoints for timed stop and motor protection.
Compare the saved minutes with the actual stop, then record the electronic indication and breaker state separately.

Keep the other applicable values as commissioned

Keep the documented defaults for the exact controller revision or the values the installer already commissioned. If TRQ appears on your panel, leave its starting torque time at that approved value. Keep current-sensor selection, marked CTS where applicable, and current or voltage calibration as commissioned. Those values belong with the installed hardware and measurements. Have the installer review changes using the matching instructions.

Ask the installer which fault restart options apply to the installed revision. Record the approved restart behavior separately from the timed-stop mode. Use the code VUKAR issues for your unit if one-time WRT registration is required. Keep the recorded mode and labels with the values so they still make sense at the next service visit.

Write down what happened during the watched run

If the pump stops before the saved RUN time, note whether the display showed a protection code and whether the MCB changed state. Report both observations. An electronic trip and an open breaker call for different checks by the installer.

BOM-H recommended parameter settings handover record with model, saved values and watched test.
Keep this information with the pump and panel paperwork.

Keep three things together for handover. First, identify the panel variant, revision, motor and water source. Second, copy the saved settings and units, including the mode that was tested. Third, write when the test started and stopped, what the display showed and any unexpected event. Date the record and add the installer’s name. This gives you a baseline if a motor, sensor or water source changes later.

If the values already in the panel and the settings on an old service sheet differ, keep both records until the installer has identified the current approved set. A note such as “read from panel” or “approved after test” tells you which numbers were observed and which ones were accepted for the installation. Leave a missing unit or value blank until it can be confirmed.

When reporting a problem, send the panel model and revision, motor rating, current mode, display code and the time of the event. Include the saved timer or protection setting that relates to the event and note any recent change in the installation. VUKAR technical support

Review the record again after the pump has worked under its usual conditions. Note any difference between the first test and later operation, including a change in flow, demand or the supply. Keep that observation as a separate dated entry. If an installer changes a setting, keep the reason for the change and the result of the next supervised run with the new record.

If you inherit the installation, identify the existing panel and pump before relying on a note left by the last owner. Find out whether the equipment was serviced or replaced after the note was written. Ask the installer to review the existing record alongside the installed hardware and to explain any change before accepting a new setting.

For a timed stop, note the time the motor actually started and when the water delivery began. The timer record describes the motor run. A separate observation of water delivery helps the installer interpret an unusual fill without changing the planned stop time. Keep the front display photo with the dated notes. Record the panel revision and the test mode next to the photo, because a display code or menu label is easiest to interpret with that information. If the display changes during the test, add when it changed and whether the pump continued to deliver water.

Use the BOM-H installation and setup guide for the panel-specific setup sequence and the VUKAR guide to pump timer types for how the different timing modes behave. At the end of the visit, keep the approved settings sheet where the next owner or technician can find it.