Borewell Handover Guide: What to Check Before You Pay or Buy a Pump

Mohit Vekaria

Before you pay for a borewell or order a pump, ask for a written drilling record and a measured pumping test. Get the actual depth, casing details, water level before and during pumping, flow and test duration. These readings help you compare what you paid for and give your pump supplier the information needed to size the system.

Before drillingCompare the same depth, casing and test scope.
At handoverCollect signed measurements and itemised charges.
Before buying a pumpUse the tested flow and pumping water level.

Compare the total quote on the same scope

Ask both contractors to quote the same bore diameter, drilling depth, casing material and grade, casing length and test scope. Check whether the drilling rate changes with depth. Ask them to write down what you owe if the bore is dry, if drilling stops early or if you approve additional depth.

Swipe sideways on smaller screens to see more columns.

Worked example for 250 ft of drilling and 60 ft of casing
Charge Quote A Quote B
Drilling 250 ft × ₹90 = ₹22,500 250 ft × ₹105 = ₹26,250
Casing 60 ft × ₹340 = ₹20,400 60 ft × ₹290 = ₹17,400
Mobilisation ₹3,500 Included
Same agreed pumping test ₹4,500 ₹2,500
Comparable total before tax ₹50,900 ₹46,150

In this illustration, Quote B costs ₹4,750 less despite the higher drilling rate per foot. The figures are examples. Ask each contractor to confirm GST, bore development, test equipment, transport and dry-bore charges in writing.

Read the pumping test before you buy the motor

Have the driller or tester record all depths from the same reference point. Ask for the flow and water level together, along with test duration and water-level recovery after stopping. A qualified tester can interpret whether the readings support your planned use.

Swipe sideways on smaller screens to see more columns.

Example borewell test readings from one reference point
Reading Example What you learn
Total drilled depth 250 ft, about 76.2 m The depth of the hole.
Static water level 16 m below ground reference Where the water stood before pumping.
Pumping water level 26 m below the same point at 60 minutes The level while pumping at the recorded test flow.
Test discharge 18 L/min The flow achieved during the test.
Recovery 18 m below reference, 20 minutes after stopping How the water level moved back after this test.

Here, drawdown at 60 minutes is 26 − 16 = 10 m. This example shows how to read a record. Ask your tester whether longer or seasonal testing is needed for your expected daily use.

Central Ground Water Board pumping test overview

Three icons for recording water level, discharge flow and elapsed test time
Record water level, flow and test duration together so the pump supplier can interpret the measured conditions.

Turn the test into a pump brief

Example for a 1,000 L overhead tank

At a steady delivered 18 L/min, fill time is about 56 minutes

If the pumping water level is 26 m below the reference and the tank inlet is 6 m above it, the vertical lift is 32 m. Add an illustrative 4 m of pipe and fitting loss at the target flow and the duty point is 18 L/min at about 36 m of head, assuming free discharge. Ask the supplier to show this point on the pump curve.

Confirm the final pump setting, bore diameter and clearance, operating water level, required flow, cable length and available electrical supply with the installer. Use the supplier’s pump curve and motor nameplate when selecting the starter.

Calculate total pump head · Check tank capacity and fill time

Printable borewell handover record

Print this section or copy it into your work order. Ask the driller and tester to complete and sign it. Keep the readings with the final invoice and pump quotation.

Swipe sideways on smaller screens to see more columns.

Borewell handover worksheet
Record Fill in at site
Site, date and contractor ________________________________
Drilled depth, diameter and reference point ________________________________
Casing material, diameter and installed length ________________________________
Static water level and time ________________________________
Test flow, duration and pumping level at timed intervals ________________________________
Recovery readings and times after stopping ________________________________
Agreed charges, exclusions and variations ________________________________
Tester and customer sign-off ________________________________

See the separate pump, cable and pipe installation costs

Quick answers

Does a deeper bore automatically need a higher-HP pump?

Select using the required flow and total head at the operating water level. Total drilled depth is one part of the installation record.

Does 18 L/min on the test guarantee that flow all year?

Use it as the measured flow under the recorded conditions. Ask the tester how season, run time and recovery affect the expected operating flow.